RWE Npower

illustration [Click image to enlarge]

Tilbury Power Station - England

Dynamic Classifier Retrofit

In November 2005, Loesche GmbH was contracted to design, supply and install five trial dynamic classifiers for Tilbury Power Station, Essex, England.

The pre-conversion Mean Rosin Rammler Slope was 49.4°, rising to 58.8° post conversion (2006).

After successfully passing the guarantee conditions, Loesche Energy Systems was awarded the subsequent contracts for units 8 & 10 (five dynamic classifiers per unit).

Unit 8 installation was successfully completed in June 2007 with unit 10 scheduled for completion in October.